| JOC Humboldt St. 9/1/21 3pm The Contract scope of work includes a collection of detailed repair and construction tasks and speci... | 08/11/2021 | 09/01/2021 | |
| Walker & Swartz Creek Culverts 8/24/21 2pm Project consists of replacing an existing corrugated metal pipe (CMP) culvert (11’ width x 7’ rise x... | 08/24/2021 | ||
| Design, Fab, Deliver 3 Bridges 8/11/21 3pm Three replacement bridge substructures, pre-engineered and prefabricated, all structural systems sha... | 08/11/2021 | ||
| E Main St Stevens Rd Parking Lot 8/10/21 10am The project consists of removal and repaving of the Church on the Hill parking lot at 400 Stevens Ro... | 08/10/2021 | ||
| Project Management 3 Rivers School District 8/25/21 2pm The Three Rivers / Josephine County Unit Joint School District invites qualified individuals or firm... | 08/25/2021 | ||
| Itroop Guardrail Replacement 8/23/21 5pm Removal and disposal of existing guardrail and posts, installation of new steel guardrail and posts ... | 08/03/2021 | 08/23/2021 | |
| Coos Bay North Jetty Repair 9/1/21 11am Proposed Coos Bay North Jetty mandatory work includes toe, side slope, and crest repair construction... | 09/01/2021 | ||
| COCC Boyle Chiller 8/26/21 4pm Remove and replace Boyle Education Center chilled water system. | 08/04/2021 | 08/26/2021 | |
| Thermal Storage Tank Design Build 8/18/21 2pm Design and construction of a Thermal Storage Tank (TES tank). Detailed scope of the work includes a... | 08/18/2021 | ||
| COCC Building 3 Boilers 8/26/21 4pm Removing existing Building 3 boilers and replacing said system. | 08/26/2021 | ||