| Title | Site Walk Through | Deadline | |
|---|---|---|---|
| Coos Bay North Jetty Repair 3/23/21 10am Includes toe, side slope, and crest repair construction above -18 feet NAVD88 elevation along 2,000 ... | 03/23/2021 | ||
| Urban Area ADA Ramp Project 4/1/21 10am Removing and replacing existing sidewalk ramps by reconstructing approximately 2740 linear feet of c... | 04/01/2021 | ||
| BLM Loon Lake Storm & Water Tank 3/26/21 12pm Remove existing Restroom A and install Government furnished CXT vault rest rooms. Includes: tree rem... | 03/16/2021 | 03/26/2021 | |
| Deadfront Padmounted Switchgears 4/6/21 2pm Deadfront Padmounted Switchgear 15 KV. | 03/23/2021 | ||
| Padmounted Transformers 4/6/21 2pm Single phase and three phase padmounted transformers for use in EWEB’s distribution system. | 04/06/2021 | ||
| Florence Center Seismic & Maint. 3/31/21 2pm Building systems analysis, seismic stabilization, deferred maintenance renovations, along with the i... | 03/31/2021 | ||
| Chetco Comm. Library Renovations 4/6/21 2pm Interior renovations to the main library area including the lobby in the Chetco Community Public Lib... | 03/23/2021 | 04/06/2021 | |
| Hemlock St. Improve Oak to Alder 3/31/21 2pm Construct approximately 390 lineal feet of new curb and gutter along the north side of Hemlock Stree... | 03/31/2021 | ||
| 42nd Street Overlay 3/25/21 2pm Grind and overlay existing asphalt roadway, construct ADA ramps, sidewalks, driveways, signage, stri... | 03/15/2021 | 03/25/2021 | |
| WWTP #1 Headworks Screen & Compactor 4/6/21 2pm Replace the ¾-inch, single-rake screen, compactor, and associated package controls at the Coos Bay W... | 03/19/2021 | 04/06/2021 | |
| Title | Site Walk Through | Deadline |
Need Help?