Stephens St. Pavement Improvements 6/1/22 2pm
The proposed work consists of pavement improvements and associated |
06/01/2022 | ||
|
SE Canyon St. Improvements 6/8/22 2pm
Cold plane pavement removal, street reconstruction, aggregate base, asphalt concrete pavement, an... |
06/08/2022 | ||
|
C St. 16 Water Main Replace 5/26/22 3pm
The Project Will Consist of The Installation of Approximately 105 Lineal Feet of 16” Water Pipe... |
05/19/2022 | 05/26/2022 | |
|
Barrel Brook Cottage Grove 6/7/22 5pm
This is a remodel of the site, exterior, and interior, of an existing 40 unit apartment complex.<... |
05/19/2022 | 06/07/2022 | |
|
Barrel Brook Grants Pass 6/7/22 5pm
This is a remodel of the site, exterior, and interior, of an existing 58 unit apartment complex.<... |
05/19/2022 | 06/07/2022 | |
|
Yurok Tribe Independent Energy Grid 6/2/22 3pm
Develop a master plan for an energy grid that will: |
06/02/2022 | ||
|
Mt. View HS Mosaic Modular Renovation 6/28/22 1pm
The relocation and placement of a modular classroom building from the Buckingham Elementary Schoo... |
06/07/2022 | 06/28/2022 | |
|
Furnish & Install Howard 6/7/22 2pm
Furnish and install a Diesel Generator at Howard Elementary School. |
05/18/2022 | 06/07/2022 | |
|
Briceland Thorne Rd. Storm Damage 6/14/22 2pm
The work to be done consists of traffic control systems, rock slope protection, culvert replaceme... |
06/14/2022 | ||
|
Yreka Community Theatre HVAC 6/1/22 2pm
The project includes, but is not limited to: Replacing the existing HVAC system; installing heat ... |
05/18/2022 | 06/01/2022 | |